Project work continues despite Mother Nature’s best efforts!

Storm Sewer Work

  • Storm sewer work is complete on Algonquin Road 
  • Storm sewer work along Randall Road is complete from Acorn/Polaris to Algonquin Road
  • Storm sewer work is ongoing on Randall Road south of Algonquin Road 

Pedestrian Tunnel Work 

  • Construction work on the pedestrian tunnel and adjacent retaining walls continues
  • Work continues on the boardwalk structure just east of the pedestrian underpass

Stone Base Work
Stone base work continues on the south side of Algonquin Road in preparation for concrete pavement

Please drive carefully through the construction zone. 