Storm Sewer and Water Main Work Underway-
Storm sewer work along Randall Road is scheduled to begin this week starting near Acorn Lane and progressing south.  Water main work is complete on Algonquin Road west of Randall Rd. Storm sewer work continues on Algonquin Rd.

Pedestrian Tunnel Work is Ongoing – 
Construction work on the pedestrian tunnel and adjacent retaining walls continue. Work has begun on the boardwalk structure just east of the pedestrian underpass.

Landscape Restoration – Topsoil placement and seeding is scheduled to begin this week, weather permitting, at the detention basin along Randall Rd. just north of Acorn Lane and along the new retaining wall, east side of Randall Rd. between Harnish Drive and Huntington Drive.

Click HERE for project photos.

Comments are disabled