Excavation and stone placement for the temporary pavement continues along the east side of Randall Road. Temporary pavement installation is scheduled to begin next week. Huntington Drive and Acorn Lane will be widened in conjunction with the temporary pavement placement on Randall Rd to allow traffic to continue in its current patterns on these side streets.
Excavation for the northbound retaining wall is complete between Harnish Drive and Huntington Drive. Piling installation at the retaining wall will continue over the next several weeks.
CLICK HERE to watch a video of the pile driving hammer in action or CLICK HERE to see photos of the pilings being installed.
All work is weather dependent.