• ComEd, Nicor, and ATT utility relocation continues.
  • Tree and brush removal has occurred where the pedestrian path will be installed between Randall Rd. and Stonegate Rd.
  • Tree and brush removal continues along the east side of Randall Rd., north of Harnish Dr. to Huntington Dr. 
    Once this area is cleared of trees and brush, the contractor will begin excavation to get ready for the new retaining wall installation.

Project work is weather dependent.  Please use caution when traveling through the work zone.