Project Update 5/1/2019

Inclement weather has slowed progress a bit this past week.  When the weather cooperates, the contractor will continue with the earth excavation, utility relocation, and temporary lighting installation. Please drive carefully through the construction zone.

More

Project Update 04/23/2019

Earth excavation continues on the east side of Randall Road in preparation for temporary pavement installation. Utility relocation and temporary lighting installation is ongoing as well.  Pothole patching is scheduled to take place later this week. Please drive carefully through the construction zone. CLICK HERE to visit the Photo webpage to see work in progress.

More

Project Update 4/16/2019

Earth excavation continues on the east side of Randall Road in preparation for temporary pavement installation. Utility relocation and temporary lighting installation is ongoing as well.  Pothole patching is scheduled to take place later this week. Please drive carefully through the construction zone.

More

Project Update 4/10/2019

Active construction is kicking into gear.  Earth excavation has begun on the east side of Randall Road in preparation for temporary pavement installation.  Please stay alert for trucks entering and leaving the area, pay attention to flaggers for directions, and drive carefully through the construction zone.

More

Project Update 4/1/2019

Beginning Tuesday, April 2, 2019, a traffic pattern shift will occur on Randall Road.  Existing medians on Randall Road were removed and temporary pavement has been placed in these areas to allow traffic to be shifted and the construction work to continue. Watch for new traffic patterns. Please proceed with caution through the work zone… Continue reading