Project Work Completed Last Week:

  • Temporary pavement was placed at the intersection of Algonquin Rd and Randall Rd to allow traffic to use the newly poured lanes
  • Curb and gutter was poured on the north leg of Randall Rd, as well as concrete driveways in the same area
  • Work started on the south bound Randall Road retaining wall, south of Bunker Hill. Pile driving and excavation were started
  • Algonquin Rd traffic was shifted onto the newly poured eastbound pavement on Friday
  • Stone was placed for the road bed on Randall Rd south of Algonquin Rd. Street lighting and traffic signal conduits were installed at the intersection as well

Project Work Scheduled for This Week:

  • Randall Rd from Algonquin Rd to Bunker Hill will be graded to prepare for concrete placement scheduled for the week of 6/15/20
  • Work on the south bound retaining wall continues
  • Permanent street lighting will be installed and activated on the south side of Algonquin Rd
  • Pavement removal will start on the north side of Algonquin Rd
  • Storm sewer work will occur on Algonquin Rd.