Overall Project Construction Progress

  • 0%


Randall Road Schedule        
       
Pre-Stage Construction        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Install temporary pavement    ·                    
Remove existing signals and lights and replace with temporary   ·                    
Detention pond work   ·                    
Construct retaining wall - eastside   ·                    
Install storm sewer - eastside   ·                    
Install pedestrian underpass eastside   ·                    
Shift traffic to the east   ·                    
Winter Shutdown        
Stage I - Southbound lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Construct retaining wall - westside     · ·                
Install storm sewer - westside     ·                  
Install pedestrian underpass - westside     ·                  
Pavement removal     · ·                
Construct southbound permanent pavement and curb & gutter       ·                
Construct temporary pavement for Stage II       ·                
Install permanent lighting - westside       ·                
Install permanent landscaping - westside       ·                
Shift traffic to westside on new pavement       ·                
Winter Shutdown        
Stage II - Northbound lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Complete detention ponds         ·              
Storm sewer         · ·            
Pavement removal         · ·            
Construct northbound permanent pavement and curb & gutter           ·            
Construct temporary pavement for Stage III           ·            
Begin permanent traffic signal install           ·            
Permanent lighting - eastside           ·            
Permanent landscaping - eastside           ·            
Shift traffic to outsides of Randall on new pavement           ·            
Winter Shutdown        
Stage III - Center lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Remove temporary pavement              ·          
Complete storm sewer             ·          
Construct permament pavement and medians             ·          
Complete traffic signal installation             ·          
Complete lighting installation             ·          
Complete permanent landscaping              ·          
Install permanent pavement striping             ·          
Open Roadway June 30, 2021        
                         



 

 

Algonquin Road Schedule      
     
Pre-Stage Construction      
Task 2018 2019 2020 2021      
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec      
Install
temporary drainage
  ·                  
Install temporary pavement    ·                  
Install storm sewer - northside   ·                  
Install temporary traffic signals   ·                  
Install temporary lighting   ·                  
Winter Shutdown      
Stage I - Eastbound lanes      
Task 2018 2019 2020 2021      
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec      
Shift
traffic to westbound lanes
    ·                
Install storm sewer - southside     ·                
Pavement removal      ·                
Construct eastbound pavement and curb & gutter     · ·              
Install permanent lighting - southside       ·              
Install permanent landscaping - southside       ·              
Winter Shutdown      
Stage II - Westbound lanes      
Task 2018 2019 2020 2021      
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec      
Shift
traffic to eastbound lanes
        ·            
Install storm sewer - northside         · ·          
Pavement removal          · ·          
Construct westbound pavement and curb & gutter         · ·          
Install permanent Lighting - northside           ·          
Install permanent landscaping - northside           ·          
Winter Shutdown      
Stage III - Center lanes      
Task 2018 2019 2020 2021      
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec      
Remove
temporary pavement 
            ·        
Complete storm sewer             ·        
Construct permament pavement and medians             ·        
Complete traffic signal installation             ·        
Complete lighting installation             ·        
Complete permanent landscaping              ·        
Install permanent pavement striping             ·        
Open Roadway June
30, 2021
     
                       



 

*Schedule is subject to change.