Overall Project Construction Progress

  • 5%






Randall
Road Schedule
Pre-Stage Construction
Task 2019 2020 2021
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Detention pond work   ·        
Construct retaining wall - eastside   ·        
Install storm sewer - eastside   ·        
Install pedestrian underpass eastside   ·        
Shift traffic to the east   ·        
Winter Shutdown
Stage I - Southbound lanes
Task 2019 2020 2021
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Construct retaining wall - westside   ·        
Install storm sewer - westside   ·        
Install pedestrian underpass - westside   ·        
Pavement removal   ·        
Construct southbound permanent pavement and curb & gutter   ·        
Construct temporary pavement for Stage II   ·        
Install permanent lighting - westside   ·        
Install permanent landscaping - westside   ·        
Shift traffic to westside on new pavement   ·        
Winter Shutdown
Stage II - Northbound lanes
Task 2019 2020 2021
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Complete detention ponds     ·      
Storm sewer     · ·    
Pavement removal     · ·    
Construct northbound permanent pavement and curb & gutter       ·    
Construct temporary pavement for Stage III       ·    
Begin permanent traffic signal install       ·    
Permanent lighting - eastside       ·    
Permanent landscaping - eastside       ·    
Shift traffic to outsides of Randall on new pavement       ·    
Winter Shutdown
Stage III - Center lanes
Task 2019 2020 2021
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Remove temporary pavement          ·  
Complete storm sewer         ·  
Construct permament pavement and medians         ·  
Complete traffic signal installation         ·  
Complete lighting installation         ·  
Complete permanent landscaping          ·  
Install permanent pavement striping         ·  
Open Roadway June 30, 2021
             








Algonquin
Road Schedule
Pre-Stage Construction
Task 2019 2020 2021
Jan -
June
July - Dec Jan - June July - Dec Jan - June July - Dec
Install
temporary drainage
·          
Install temporary pavement  ·          
Install storm sewer - northside ·          
Winter Shutdown
Stage I - Eastbound lanes
Task 2019 2020 2021
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Shift
traffic to westbound lanes
·          
Install storm sewer - southside ·          
Pavement removal  ·          
Construct eastbound pavement and curb & gutter · ·        
Install permanent lighting - southside   ·        
Install permanent landscaping - southside   ·        
Winter Shutdown
Stage II - Westbound lanes
Task 2019 2020 2021
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Shift
traffic to eastbound lanes
    ·      
Install storm sewer - northside     · ·    
Pavement removal      · ·    
Construct westbound pavement and curb & gutter     · ·    
Install permanent Lighting - northside       ·    
Install permanent landscaping - northside       ·    
Winter Shutdown
Stage III - Center lanes
Task 2019 2020 2021
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Remove
temporary pavement 
        ·  
Complete storm sewer         ·  
Construct permament pavement and medians         ·  
Complete traffic signal installation         ·  
Complete lighting installation         ·  
Complete permanent landscaping          ·  
Install permanent pavement striping         ·  
Open Roadway June 30,
2021
             



*Schedule is subject to change.