Randall Road Schedule        
       
Pre-Stage Construction        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Install temporary pavement    ·                    
Remove existing signals and lights and replace with temporary   ·                    
Detention pond work   ·                    
Construct retaining wall - eastside   ·                    
Install storm sewer - eastside   ·                    
Install pedestrian underpass eastside   ·                    
Shift traffic to the east   ·                    
Winter Shutdown        
Stage I - Southbound lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Construct retaining wall - westside     · ·                
Install storm sewer - westside     ·                  
Install pedestrian underpass - westside     ·                  
Pavement removal     · ·                
Construct southbound permanent pavement and curb & gutter       ·                
Construct temporary pavement for Stage II       ·                
Install permanent lighting - westside       ·                
Install permanent landscaping - westside       ·                
Shift traffic to westside on new pavement       ·                
Winter Shutdown        
Stage II - Northbound lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Complete detention ponds         ·              
Storm sewer         · ·            
Pavement removal         · ·            
Construct northbound permanent pavement and curb & gutter           ·            
Construct temporary pavement for Stage III           ·            
Begin permanent traffic signal install           ·            
Permanent lighting - eastside           ·            
Permanent landscaping - eastside           ·            
Shift traffic to outsides of Randall on new pavement           ·            
Winter Shutdown        
Stage III - Center lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Remove temporary pavement              ·          
Complete storm sewer             ·          
Construct permament pavement and medians             ·          
Complete traffic signal installation             ·          
Complete lighting installation             ·          
Complete permanent landscaping              ·          
Install permanent pavement striping             ·          
Open Roadway June 30, 2021        
                         



 


<![if supportMisalignedColumns]><![endif]>

Randall Road Schedule        
       
Pre-Stage Construction        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Install temporary pavement    ·                    
Remove existing signals and lights and replace with temporary   ·                    
Detention pond work   ·                    
Construct retaining wall - eastside   ·                    
Install storm sewer - eastside   ·                    
Install pedestrian underpass eastside   ·                    
Shift traffic to the east   ·                    
Winter Shutdown        
Stage I - Southbound lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Construct retaining wall - westside     · ·                
Install storm sewer - westside     ·                  
Install pedestrian underpass - westside     ·                  
Pavement removal     · ·                
Construct southbound permanent pavement and curb & gutter       ·                
Construct temporary pavement for Stage II       ·                
Install permanent lighting - westside       ·                
Install permanent landscaping - westside       ·                
Shift traffic to westside on new pavement       ·                
Winter Shutdown        
Stage II - Northbound lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Complete detention ponds         ·              
Storm sewer         · ·            
Pavement removal         · ·            
Construct northbound permanent pavement and curb & gutter           ·            
Construct temporary pavement for Stage III           ·            
Begin permanent traffic signal install           ·            
Permanent lighting - eastside           ·            
Permanent landscaping - eastside           ·            
Shift traffic to outsides of Randall on new pavement           ·            
Winter Shutdown        
Stage III - Center lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Remove temporary pavement              ·          
Complete storm sewer             ·          
Construct permament pavement and medians             ·          
Complete traffic signal installation             ·          
Complete lighting installation             ·          
Complete permanent landscaping              ·          
Install permanent pavement striping             ·          
Open Roadway June 30, 2021        
                         



 


Randall Road Schedule        
       
Pre-Stage Construction        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Install temporary pavement    ·                    
Remove existing signals and lights and replace with temporary   ·                    
Detention pond work   ·                    
Construct retaining wall - eastside   ·                    
Install storm sewer - eastside   ·                    
Install pedestrian underpass eastside   ·                    
Shift traffic to the east   ·                    
Winter Shutdown        
Stage I - Southbound lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Construct retaining wall - westside     · ·                
Install storm sewer - westside     ·                  
Install pedestrian underpass - westside     ·                  
Pavement removal     · ·                
Construct southbound permanent pavement and curb & gutter       ·                
Construct temporary pavement for Stage II       ·                
Install permanent lighting - westside       ·                
Install permanent landscaping - westside       ·                
Shift traffic to westside on new pavement       ·                
Winter Shutdown        
Stage II - Northbound lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Complete detention ponds         ·              
Storm sewer         · ·            
Pavement removal         · ·            
Construct northbound permanent pavement and curb & gutter           ·            
Construct temporary pavement for Stage III           ·            
Begin permanent traffic signal install           ·            
Permanent lighting - eastside           ·            
Permanent landscaping - eastside           ·            
Shift traffic to outsides of Randall on new pavement           ·            
Winter Shutdown        
Stage III - Center lanes        
Task 2018 2019 2020 2021        
Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec        
Remove temporary pavement              ·          
Complete storm sewer             ·          
Construct permament pavement and medians             ·          
Complete traffic signal installation             ·          
Complete lighting installation             ·          
Complete permanent landscaping              ·          
Install permanent pavement striping             ·          
Open Roadway June 30, 2021